Las Vegas Schedule





Project Start:
Project Finish:
Mon 2/5/01
Mon 6/4/01


Task_Table1


IDTask_NameBaseline_DurBaseline_StartBaseline_Finish
1
SiteWork
93 daysMon 1/22/01Wed 5/30/01
2
Site prep/Grading
13 daysMon 1/22/01Wed 2/7/01
3
Sidewaks
2 wksMon 4/23/01Fri 5/4/01
4
Curbs
3 daysWed 5/16/01Fri 5/18/01
5
Paving
1 wkThu 5/10/01Wed 5/16/01
6
Fine Grade
3 daysFri 5/18/01Tue 5/22/01
7
Landscaping
7 daysTue 5/22/01Wed 5/30/01
8
Building
82 daysThu 2/8/01Mon 6/4/01
9
Footings
17 daysThu 2/8/01Fri 3/2/01
10
Foundation Blocks
2 daysFri 3/2/01Mon 3/5/01
11
Slab Prep
15 daysMon 3/5/01Fri 3/23/01
12
Pour slab
1 dayMon 3/26/01Mon 3/26/01
13
Structural Steel
11 daysMon 3/5/01Mon 3/19/01
14
Exterior walls
2 wksTue 3/27/01Mon 4/9/01
15
Roof blocking
7 daysMon 4/2/01Tue 4/10/01
16
Roofing
1 wkWed 4/11/01Tue 4/17/01
17
Masonry
2 wksFri 4/20/01Thu 5/3/01
18
Dryvit
2 wksMon 4/9/01Fri 4/20/01
19
Dryvit bands
3 daysThu 5/3/01Mon 5/7/01
20
Interior wall framing
10 daysMon 4/9/01Fri 4/20/01
21
MPE Rough in
3 wksMon 4/9/01Fri 4/27/01
22
Storefront
1 wkThu 5/3/01Wed 5/9/01
23
Sheetrock
2 wksMon 4/23/01Fri 5/4/01
24
Restroom floors
2 daysFri 5/4/01Mon 5/7/01
25
Priming
2 daysFri 5/4/01Mon 5/7/01
26
Ceiling grid
3 daysMon 5/7/01Wed 5/9/01
27
Frames
4 daysFri 5/4/01Wed 5/9/01
28
Painting
2 wksMon 5/7/01Fri 5/18/01
29
Celing tiles
1 wkMon 5/21/01Fri 5/25/01
30
Carpet/LVG finishes
1.5 wksFri 5/18/01Tue 5/29/01
31
Doors
4 daysFri 5/18/01Wed 5/23/01
32
Hardware
2 daysWed 5/23/01Thu 5/24/01
33
Fire ext./Misc.
3 daysThu 5/24/01Mon 5/28/01
34
Inspections
3 daysMon 5/28/01Wed 5/30/01
35
Completion date
0 daysMon 6/4/01Mon 6/4/01
36
Mechanical
51 daysThu 3/22/01Thu 5/31/01
37
Set curbs
2 daysThu 3/22/01Fri 3/23/01
38
Set units
2 daysWed 4/18/01Thu 4/19/01
39
Ductwork
2 wksMon 4/23/01Fri 5/4/01
40
Registers
1 wkWed 5/9/01Tue 5/15/01
41
Inspections
2 daysWed 5/30/01Thu 5/31/01
42
Plumbing
54 daysMon 3/19/01Thu 5/31/01
43
Slab Rough in
5 daysMon 3/19/01Fri 3/23/01
44
City connection
1 wkMon 4/2/01Fri 4/6/01
45
Wall rough in
3 wksMon 4/16/01Fri 5/4/01
46
Set fixtures
1 wkMon 5/7/01Fri 5/11/01
47
Inspections
2 daysWed 5/30/01Thu 5/31/01
48
Electrical
53 daysMon 3/19/01Wed 5/30/01
49
Slab rough in
5 daysMon 3/19/01Fri 3/23/01
50
City connection
1 wkMon 4/2/01Fri 4/6/01
51
Ext Wall rough in
1 wkTue 4/3/01Mon 4/9/01
52
Interior wall rough in
2 wksMon 4/9/01Fri 4/20/01
53
Lights
2 wksWed 5/9/01Tue 5/22/01
54
Trim out
1 wkTue 5/22/01Mon 5/28/01
55
Inspections
3 daysMon 5/28/01Wed 5/30/01